Project Name:
Panther Creek Expansion
North Texas MWD
Scope of Work:
Additions and modifications to the existing Wastewater Treatment Plant to
increase capacity to 10 MGD.
o $17,992,706.00
o Start Date March 2009
Estimated Completion Date December 2010
Project Manager: Roy Ewen
Project Supervision: Bill Bigham
Project Name:
Rolling Hills Filter Modifications
City of Fort Worth, Texas
Scope of Work:
Modifications and renovation of filters 1 through 20 at the Rolling Hills Water
Treatment Plant.
o $497,250.00
o Start Date February 2009
Estimated Completion Date July 2009
Project Manager: Andy Howard
Project Supervision: Juan Rodriguez
Project Name:
MacArthur Pump Station
City of Irving, Texas
Scope of Work:
Construction of a new Pump Station, including appurtenant yard piping, meter
vaults, electrical, instrumentation, site work, and demolition.
o $14,625,000.00
o Start Date January 1, 2009
Estimated Completion Date June 2010
Project Manager: Billy Haynes
Project Supervision: Ben Lane
Project Name:
TRA Solids Handling Improvements
Trinity River Authority of Texas
Scope of Work:
Addition of new Gravity Belt Thickener, Pumps and Storage Facilities at an
existing facility.
o $4,556,000.00
o Start Date May 15, 2008
Scheduled Completion Date December 15, 2009
Project Manager: Mike Smith
Project Supervision: Rogelio Obregon
Project Name:
Denton Creek Regional Wastewater System Expansion
Trinity River Authority of Texas
Scope of Work:
Addition of a new Wastewater Train and modifications to existing facilities to
increase capacity to 11.5 MGD.
o $38,079,000.00
o Start Date April 2008
Scheduled Completion Date July 2010
Project Manager: Arthur Daugherty
Project Supervision: Steve Baker
Project Name:
Southeast Water Reclamation Plant Improvements
City of Lubbock, Texas
Scope of Work:
Modifications and additions to the existing wastewater plant to increase current
capacity.
o $43,520,000
o Start Date April, 2008
Scheduled Completion Date March, 2011
Project Manager: Glenn Grant
Project Supervision: Ron Bray
Project Name:
Central Regional Wastewater System
Trinity River Authority of Texas
Scope of Work:
Construction of new process Pump Station 13 B, modifications to Pump
Station 13, hydraulic piping improvements and modifications to the Aeration
and Equalization Basins. Also included are modifications to the plant entrance
and Liquids Operation Center.
o $23,554,796
o Awarded August 22, 2007
o Scheduled Start Date October 8, 2007
Scheduled Completion Date October 2009
Project Manager: Roy Ewen
Project Supervision: Luis Aguilar
Eagle Contracting, L.P.